Carry-Over-Work (COW) |
Carry-Over-Work (COW) item is work that has not been completed at the fabricator/manufacturer and is the responsibility of that party to complete. Carry-Over-Work items will be recorded and tracked in the CCMS Database, as part of the Punchlist Manager module. |
Commissioning |
The phase of the project that transfers a facility from a construction site to an operational facility. |
Completions and Commissioning Management System (CCMS) |
A database system that tracks Mechanical Completion, Pre-Commissioning and Commissioning activities and data, including Punchlisting. |
Field Installation Checklist (FIC) |
Also known as Mechanical Completion Check Records (MCCRs). FICs are detailed documents that allow essential data to be recorded in a standardized format, providing documentary evidence of mechanical completion activities. |
Industrial Business Solutions |
Software developer for Continuum Edge-Completions and Commissioning Management System. |
Inspection Test Record (ITR) |
ITR is a detailed document that allows essential data to be recorded in a standardized format, providing documentary evidence of pre-commissioning activities. |
Job Card |
A collection of tasks and / or forms that are combined into a Job Card where they have common attributes, such as system / subsystem boundaries, project phase / stage and associated workgroup requirements. |
Job Cards Manager |
Designed to manage the assignment and administration of a collection of Job Cards. |
Sub-System |
The facility systems, as defined below, are further divided into sub-systems, where appropriate, in order to facilitate the Mechanical Completion, Function Testing, Commissioning and Handover of the entire Facility. |
System |
Process System – a test area or section defined by specific process application, pressure and/or temperature, or by specific hazards. Non-Process System – an infrastructure, such as buildings, structures, concreting and electrical and communications equipment. |
Task / Planned Task |
Individual FICs or ITRs that have been created for each asset that is required to be completed during different phases i.e. Fabrication, Construction, Pre-Commissioning and Commissioning. |
Mechanical Completion (MC) |
The state of the system when all civil, structural, concrete, piping, electrical, instrumentation and mechanical items have been installed as per the design documents and codes |
Project |
CAPEX or OPEX Project that is supported with the CCMS |
Punchlist ‘A’ |
Punchlist ‘A’ item prevents the sub-system or system from being Pre-commissioned, Commissioned or energised due to constraints on operability or safety of either PERSONNEL, EQUIPMENT or ENVIRONMENT. |
Punchlist ‘B’ |
Punchlist ‘B’ item can, by agreement, be rolled over to the next phase. ‘B’ items shall not prevent the safe operation of the equipment &/or system but represents incomplete work. |
Punchlist ‘C’ |
Punchlist ‘C’ item can be repaired and/or completed after handover, but must be done before issuance of the Close-out Certificate (C6). |
Pre-commissioning |
The phase of the project that involves a set of checks to prove the system functionality and prepares the system for commissioning. |
Work Package |
A work package comprised of one or more tasks. Each task can identify specific person(s), tools, materials, safety requirements and supportive documentation. A work package is summarized in a simple go or no-go Job Card. |
Work Package Manager |
A Work Package manager is designed to manage the development, scheduling and execution of Work or Jobs. |