Work Breakdown Tree (WBS)

FAQs  | Feedback


A Work Breakdown Structure (WBS), in project management and systems engineering, is a deliverable-oriented decomposition of a project into smaller components.  In this case projects are always based on Phases, Stages and Activities (level 3).  Level 4 tasks are tracked in the PCT module and is where P6 schedules would be imported and manipulated.  Level 5 tasks are tracked in the CCMS management suite.


The process for developing Project Work Breakdown Structure (WBS) is outlined below:


 Step

  Action

  1

Navigation:  Configuration > Trees/Tasks > Work Breakdown Tree


It will then display icons that are considered “Core” configuration modules.  Setting up a project will require at a minimum of a Work Breakdown Structure (WBS) which will contain:


  • Phases
  • Stages
  • Activities (optional)



The WBS module is a core module within the CE foundation and is ONLY ACCESSED via the CE homepage (switchboard).  


Note:  To access the WBS tool, a project must be selected from the Organization Chart.



Phase Edit Form.

 2

ENTER PHASE: To create the first phase of the WBS, press the NEW LEAF button and enter in the Number and Name (description) of the Phase.




Select “Is Front End Loading” if this phase is a pre-execution phase as it will determine which detailed report is attached to the PPM monthly report.



Note: Enter in planned START and END dates if they are available, as they are used in several reports.


Stage Edit Form.

 3

ENTER STAGE:  Left click the PHASE and press the NEW LEAF button to enter in a STAGE for the selected phase.




Enter in the number “CO.1” for the number and “Business Review” for the name.  You will notice the “Level” is set to STAGE.  Press SAVE to commit the STAGE to the WBS.


Note: Enter in planned START and END dates if they are available, as they are used in several reports.


Activity Edit Form.

 4

ENTER ACTIVITY:  Left click the STAGE and press the NEW LEAF button to enter in an ACTIVITY for the selected phase.




Enter in the number “CO.1.01” for the number and “Level 2 Cost Definition” for the name.  You will notice the “Level” is set to ACTIVITY.  Press SAVE to commit the ACTIVITY to the WBS.


Next Training:  Physical Location Tree (LBS)