Importing a Work Breakdown Structure (WBS) for a Project can expedite the creation and updating of the WBS items (a.k.a. phases, stages). Since WBS items are much less than systemization structures, we recommend that the interface is used to develop the structure. If there is a lengthy list of WBS items (say > 15) then importing the WBS phases, stages and activities can reduce time to create.
When importing the WBS tree, it must be performed in two (2) different imports:
It is important the systemization XLS file have the following columns:
Important Notes:
The process for importing Work Breakdown Structure (WBS) is outlined below:
Step |
Action |
1 |
Switchboard Navigation: Configuration > Data Exchange > Imports Menu Navigation: Engineering > General Configuration > Imports Import Wizard Button. |
2 |
Select IMPORT TYPE view to import against (do not select hyperlink). The Import Type for importing a PCT list is named Project Control Tasks
Import Edit Form - Browse to File. |
3 |
Select CHOOSE FILE to browse and select a file (.xls) file to upload into the CE database. Browse to the XLS file just as if you were attaching an image to a document, it is the same concept.
After mapping the fields, the import tool will perform a “Pre-Import” validation process, where it will present the what the results will be prior to committing to the import. This is an important feature as it will allow a user to cancel the import as they identified issues if they had proceeded directly with the import. Press NEXT to map fields. Import Edit Form - Map Fields (First Import). |
4 |
The FIRST IMPORT will focus on importing the list of Process Breakdown nodes. The fields that MUST to be mapped are:
NOTE: The collision behavior is designed to set the business rules for the instance where data already exists in the database. If a record finds a perfect match against the NAME field, then it will apply a collision behavior, where:
Press FINISH to process the XLS file into the database. Important Notes:
After importing the list of nodes, you can confirm by reviewing the number of INSERTS it created in the database. Import Edit Form - Map Fields (Second Import). |
5 |
The SECOND IMPORT will focus on creating the parent – child relationships between the systemization nodes. Follow the same actions as defined in Step 4. CE will require the same mapping as the first import.:
Important Notes:
Import Log. |
6 |
READING THE IMPORT LOG (results): Each import will be summarized in the import log. Select the blue Hyperlink to load the results from any import against this import view. A user can also select the XLS icon to load the file that was processed. After importing the PCT list a user will see the PCT list created and if completion details (actual end date) is entered it will automatically assign the PCT a completion status. If a user did not put in “completed by” in the XLS it will insert the name of the person importing the XLS file. Next Training: View Import Log |